BEGIN:VCALENDAR VERSION:2.0 PRODID:-//jEvents 2.0 for Joomla//EN CALSCALE:GREGORIAN METHOD:PUBLISH BEGIN:VTIMEZONE TZID:Europe/London BEGIN:STANDARD DTSTART:20220201T090000 RDATE:20220327T020000 TZOFFSETFROM:+0100 TZOFFSETTO:+0000 TZNAME:Europe/London GMT END:STANDARD BEGIN:STANDARD DTSTART:20221030T010000 RDATE:20230326T020000 TZOFFSETFROM:+0100 TZOFFSETTO:+0000 TZNAME:Europe/London GMT END:STANDARD BEGIN:STANDARD DTSTART:20231029T010000 RDATE:20240331T020000 TZOFFSETFROM:+0100 TZOFFSETTO:+0000 TZNAME:Europe/London GMT END:STANDARD BEGIN:STANDARD DTSTART:20241027T010000 RDATE:20250330T020000 TZOFFSETFROM:+0100 TZOFFSETTO:+0000 TZNAME:Europe/London GMT END:STANDARD BEGIN:STANDARD DTSTART:20251026T010000 RDATE:20260329T020000 TZOFFSETFROM:+0100 TZOFFSETTO:+0000 TZNAME:Europe/London GMT END:STANDARD BEGIN:DAYLIGHT DTSTART:20220327T020000 RDATE:20221030T010000 TZOFFSETFROM:+0000 TZOFFSETTO:+0100 TZNAME:Europe/London BST END:DAYLIGHT BEGIN:DAYLIGHT DTSTART:20230326T020000 RDATE:20231029T010000 TZOFFSETFROM:+0000 TZOFFSETTO:+0100 TZNAME:Europe/London BST END:DAYLIGHT BEGIN:DAYLIGHT DTSTART:20240331T020000 RDATE:20241027T010000 TZOFFSETFROM:+0000 TZOFFSETTO:+0100 TZNAME:Europe/London BST END:DAYLIGHT BEGIN:DAYLIGHT DTSTART:20250330T020000 RDATE:20251026T010000 TZOFFSETFROM:+0000 TZOFFSETTO:+0100 TZNAME:Europe/London BST END:DAYLIGHT END:VTIMEZONE BEGIN:VEVENT UID:46e7d57ad46b939537e0562c804eb8bf CATEGORIES:Events CREATED:19700101T010000 SUMMARY:Temporary road closure - Forest Road, Wootton Rivers DESCRIPTION:
Keep up to date with real-time changes to this closure at https://one.network/?GB132332826
Carriageway re pair works programmed on Wootton Rivers, Pewsey. The site extent s can be viewed on the drawing:
These works involve asphalt patch repairs, adjustment of ironwork
, reinstatement of road markings and associated maintenance works.
p>
The works will commence on Thur sday the 2nd of February 2023 and will be completed by Sunday the 5th of Fe bruary 2023 between the hours of 09:00 and 15:00, however on occas ions they may over run due to uncontrollable circumstances such as plant br eakdowns, if weather conditions are unfavourable, or occasionally we discov er the need for additional repairs once the work has started. Th ere will be advance information signs erected on site giving confirmed star t dates.
Due to the nature of t he works and the local environment, the works will be carried out within a temporary road closure, to ensure that adequate health & safety is main tained for the contractor & local residents. Road Markings a nd Ironwork adjustments may need to be completed at a later date.
The main diversion route for all ‘through’ traffic whilst works are bei ng undertaken within the road closure will be as per the diversion drawing:
The Contractor will mainta in pedestrian access for residents for the duration of the works; but depen ding upon what operation is being undertaken and where it’s being undertake n residents may find that when accessing or egressing from their property i n their vehicle, they may experience a delay and have to wait for plant to be moved out of the carriageway. Residents, when leaving their property, sh ould allow extra time for any possible delays and when returning to their p roperty, there will be traffic management operatives located at the extents of the works, to speak to them, explain where they live, and they will be able to assist.
There will be p
oints during the material laying process where vehicular access will be res
tricted as residents won’t be able to drive over the newly laid material, a
s early trafficking could lead to premature failure, therefore it is recomm
ended to residents that if works are being undertaken in the vicinity of th
eir property to speak to the workforce in advance to ask if there will be a
ny restrictions with regards to access.
Advanced signing will b
e erected and letter drops to all residents located within the site extents
will commence week starting 16th of January 2023. Signing will be in place
advising that local businesses will be open as usual.
Wiltshire Council would like to take this opportuni
ty to apologise for any inconvenience these works will cause but trust driv
ers will appreciate the necessity for these essential works to maintain Wil
tshire's highway network.
Should you require any further information
in advance of the works please refer to (https://one.network/?GB132332826). If you wish to discuss the
works whilst they are in operation, please speak to a member of the workfor
ce who will direct you to the appropriate person on site.